Frequently Asked Questions
Please note: This FAQ is an evolving document and will be updated as new information becomes available and/or new questions as submitted.
Please submit your questions to FS1committee@westwoodma.gov.
-
The current concept from designers KBA would see the FS1 facility in the northwestern corner of the parcel, preserving the existing Deerfield building and minimizing loss of field space (approx. reduction from 3.3 acres today to ≈2.9 with FS1). This is an early design and will be refined and adjusted publicly throughout summer and fall.
-
Yes, and it can do so with a significantly smaller building than the 2025 proposal. The site’s large size and flat layout will also make drive-thru / back-to-back fire apparatus bays possible, dropping the proposed program from 5 bays to only 4. This will help reduce the building size and construction cost while maximizing the operational use of each space for the Fire Department.
-
Deerfield is an existing, developed municipal site with a large, relatively flat area that provides several advantages for construction.
The site avoids some of the most significant challenges associated with other locations, including:
Significant clearing of undeveloped land;
Large changes in site elevation;
Complex site and lot size constraints;
Possible land takings or easement acquisitions;
Extensive temporary operational planning and spending during construction.
These factors contributed to Deerfield having the lowest estimated range of possible project cost when compared to the existing site and the land behind Starbucks.
-
The Deerfield site will allow the new FS1 to comply with Westwood’s zoning to a significantly improved degree compared to a station on the existing site.
-
Yes. Wetland resource areas were identified and mapped by qualified wetland scientists as part of the pre-feasibility assessment.
The existing Deerfield site was largely designed and constructed prior to modern stormwater control standards. The new FS1 project must comply with those new and improved standards.
Additional public review and permitting, including wetland, stormwater and any applicable environmental review, will occur as design progresses.
-
Preserving recreation opportunities at Deerfield is a priority.
The current concept evaluates a reduction in total field area from approximately 3.3 acres today to approximately 2.9 acres while creating opportunities for improved field conditions through:
Better drainage and grading;
Improved playability;
More intentional field design.
Based on community feedback, the current concept maintains two softball fields (but upsizes them to regulation size), a multiuse field, and a walking path. However, the actual best use for the field space is not set in stone and the Town through the Select Board is interested in hearing from the community on recreational preferences as we develop this vision.
The Town will continue working with the Recreation Department, youth sports organizations, and neighbors to understand community priorities for future field layouts and programming. Any future decisions involving changes to field size or programming will be presented publicly with a clear explanation of the benefits and/or tradeoffs.
-
The current concept does not anticipate demolishing the former school facility or eliminating the flexible use of programs inside the facility (Westwood Recreation, IT Department).
The modular trailers currently used by Westwood Media Center may need to be removed as part of the site plan. Town officials are evaluating options to relocate the organization into available, unused classroom space within the existing building, within the project budget.
The Town is committed to coordinating with Westwood Media Center, the Recreation Department, and other community users to maintain important indoor and outdoor community uses at the site.
-
Multiple access options are being evaluated. The current concept would primarily utilize the existing Police Department access road for dispatching fire apparatus to High Street. The curb cut to High Street would be enhanced and pre-emption signals added for the safety of motorists.
Dead-ending Deerfield Avenue is not required for the FS1 project. Early concepts included a potential dead-ending of Deerfield Ave based on preliminary neighborhood feedback. Appreciating neighborhood and community concerns about impact on traffic, that concept is no longer carried in the site plan.
The Fire Chief has committed that Fire and EMS would only use Deerfield Ave to respond to calls if there was an emergency on Deerfield Ave or in the immediately adjacent area.
Additional traffic and access considerations will be reviewed by project engineers and the Fire Department and shared with the public as the new FS1 advances through design.
-
The size and location of the Deerfield property provide multiple opportunities for parking solutions, including consideration of nearby publicly owned parking resources. The current concept also includes restoration of the existing walking path, currently a crushed gravel path.
-
The FS1 project at Deerfield will prioritize preserving and, where possible, enhancing:
Outdoor recreation opportunities;
Community programming within the former school building (Recreation Dept);
Future flexibility for municipal needs.
Doing so co-locates many municipal uses including Police, Fire, Town Hall, the Westwood Public Library and existing flex space in the Deerfield building. Future planning decisions related to Thurston Middle School, Council on Aging space needs, recreation programming, and other municipal priorities will continue to inform long-term planning for the site.
-
With the site selected, the new FS1 will enter the Schematic Design phase. Residents will receive updated information including project cost, financing sources, projected residential tax impact, and schematic building and site designs prior to voting in October and November. These specifics will undergo significant public review with the Select Board and Finance & Warrant Commission leading up to the October Special Town Meeting.
Deerfield
Feasibility, Design, and Project Development
-
The 2023 feasibility study focused primarily on rebuilding Fire Station 1 at its existing location.
While several other sites received limited review, the former Deerfield School property was not evaluated as part of that study. Additional feasibility analysis was necessary to ensure all viable alternatives received a fair and comprehensive review.
Now that Deerfield has been selected as the preferred site, additional feasibility work and schematic design are underway. This work includes engineering, environmental review, utility analysis, traffic evaluation, site planning, and detailed cost estimating that were not completed as part of the 2023 study.
The purpose of this work is to develop a site-specific design and cost estimate that can be presented to voters this fall.
-
The pre-feasibility study, which was conducted during the spring and summer of 2026, evaluated whether the potential FS1 sites under consideration warranted further investigation.
The assessment concluded that both the Deerfield School property and Town-owned Parcel 14-131 appeared capable of accommodating a modern fire station based on preliminary engineering, zoning, environmental, and access reviews.
The purpose of the study was not to select a site, but rather to determine which locations warranted further evaluation. Following additional analysis, public input, and Steering Committee review, the Deerfield School property was ultimately selected as the preferred site.
-
No.
Any plans, renderings, or layouts prepared to date are conceptual and were developed to determine whether a fire station could reasonably fit on the site.
The Town is currently developing a schematic design for the Deerfield site. Final design work will occur only after voter approval and will continue through subsequent design phases.
-
Now that the Deerfield School property has been selected as the preferred site, the project team is focused on completing the feasibility and schematic design work necessary to provide voters with a well-developed proposal.
Between August and the October Town Meeting and November election, the Town's consultants are completing:
Site engineering and layout design
Traffic analysis
Utility investigations
Environmental review
Wetland and permitting evaluations
Building design and floor plan development
Construction cost estimating
Financial analysis and tax impact modeling
Public outreach and community engagement
This work will allow the Town to create a site-specific design, refine a project budget, and develop an estimated impact on taxes prior to voters making a decision.
-
Selecting a preferred site is an important milestone, but it is not the final approval to make a new Fire Station 1 a reality.
The Fire Station 1 project team is now completing feasibility work and schematic design for the Deerfield site. This effort will allow the Town to:
Refine project costs
Determine estimated residential tax impacts
Complete environmental and engineering reviews
Finalize site layout concepts
Continue public engagement and outreach
The project must still receive approval from voters both at a Town Meeting and through a debt exclusion ballot question before construction can proceed.
-
Architectural and engineering services are provided by Kaestle Boos Associates (KBA), working in coordination with the Town, the Fire Department, and the Owner's Project Manager (OPM), PMA Consultants.
-
The OPM, PMA Consultants, represents the Town's interests throughout the project and assists with:
Budget management
Schedule management
Project coordination
Procurement oversight
Quality control
Risk management
The OPM serves as an independent advisor to help ensure the project remains aligned with Town goals.
-
No decision has been made regarding the future use of the existing Fire Station 1 property at 637 High Street.
The Town will evaluate future municipal needs, facility requirements, zoning considerations, and potential redevelopment opportunities.
Any sale of Town-owned property would require approval by Town Meeting. Any future zoning changes would also require approval through the Town's public process.
The future use of the property will be considered as part of the Town's broader long-range facilities and capital planning efforts.
-
A modern fire station must accommodate:
Apparatus bays sized for current and future vehicles
Living quarters for 24-hour staffing
Decontamination facilities
Administrative offices
Training space
Equipment storage
Support and maintenance functions
These needs reflect modern fire service standards and firefighter health and safety requirements. Click here to read the committee’s Documentation of FS1’s Programmatic Needs.
-
Yes.
The program has been developed using industry standards, fire service best practices, operational analysis, and input from Fire Department leadership and professional consultants. You can find documentation of the programmatic needs here.
-
Yes.
Response data, call volume, and service demand patterns have been key factors in evaluating potential station locations.
-
Training is a critical component of fire and EMS operations and is required by numerous state and federal regulations.
The proposed training room would be used for:
Department-wide fire and rescue training
EMS continuing education
Tabletop emergency management exercises
Incident command training
Critical incident stress debriefings
Meetings involving multiple shifts and personnel
Many firefighter and paramedic certifications that require continuing education and recurring training throughout the year.
-
Today, the Department often relies on borrowed space, including the Main Library meeting room, for larger training sessions as the existing training space at Fire Station 1 is not sufficient.
While these external facilities are helpful, they were not designed for fire department operations and can present scheduling, logistical, and operational challenges.
Dedicated training space within the station would improve training efficiency while ensuring personnel and apparatus remain readily available for emergency response.
-
No.
Fire Station 2 was designed as a substation rather than a headquarters facility and does not contain a dedicated conference room or training room where large groups of firefighters can gather for meetings, training, or department-wide activities.
The station does include a training staircase that is used for certain hands-on and operational training exercises. However, it does not provide the classroom, meeting, or multi-purpose training space needed to support larger training programs, department meetings, or other functions typically accommodated in a headquarters fire station.
-
The primary driver of the increased size is not an expansion of staffing or services. Rather, it is that the existing station is significantly undersized and no longer meets modern fire service standards.
The current station was designed decades ago for a smaller department with smaller apparatus and different operational requirements. Today's fire service requires:
Apparatus bays to accommodate larger vehicles
Decontamination facilities
Dedicated training space
Modern firefighter health and safety features
Adequate storage for equipment
Appropriate living quarters for 24-hour staffing
Accessible and code-compliant facilities
Even after reducing the building program by approximately 20% from the 2025 proposal, the new facility will still be larger than the existing station because it lacks many of the spaces required for modern fire department operations.
Fire Station Need and Operations
Maintenance Bay
-
The maintenance bay provides a cost-effective way to maintain the Fire Department's apparatus fleet and maximize vehicle availability for emergency response.
Maintaining apparatus is a core operational requirement of any fire department. The Town must either perform this work in-house or pay private vendors to perform repairs.
In-house maintenance generally:
Reduces repair costs
Reduces apparatus downtime
Improves emergency readiness
Protects the Town's investment in expensive emergency vehicles
The Fire Department currently performs maintenance in-house and intends to continue doing so.
-
The proposed maintenance bay within the fire station project is estimated to cost approximately $2.1 million.
Constructing a separate stand-alone maintenance facility would be substantially more expensive and is estimated to cost approximately $7 million.
In addition, no Town-owned site has been identified that can accommodate a stand-alone apparatus maintenance facility without significant cost, permitting, or operational challenges.
The Police Department garage, DPW facilities, and other Town-owned properties do not have the size or structural capacity necessary to service fire apparatus.
-
Maintaining fire apparatus and emergency vehicles is critical to ensuring reliable emergency response. While major repairs will continue to be performed by specialized vendors, having appropriate on-site maintenance space allows Fire Department staff to perform routine inspections, preventative maintenance, equipment installations, and minor repairs more efficiently.
When vehicles must be sent out of town for service, costs can be significant and apparatus may be unavailable for extended periods. Recent examples include:
September 2024 – Engine 5 Repairs: Labor rate of $213 per hour; vehicle out of service for approximately 5 weeks.
May 2024 – Engine 2 Repairs: Labor rate of $213 per hour; vehicle out of service for approximately 4 weeks.
January 2024 – Ambulance Repairs: Labor rate of $179 per hour; vehicle out of service for approximately 6 weeks.
Providing functional maintenance space within the station helps reduce reliance on outside vendors for minor work, improves efficiency, and can minimize the amount of time emergency vehicles are unavailable for service.
-
No.
Given the shape and geography of the Town, Fire Station 2 is an essential component of Westwood's emergency response system and provides critical coverage to the Islington area and surrounding neighborhoods.
Fire Station 2 does not have sufficient capacity to permanently absorb the apparatus, personnel, administrative functions, training functions, and support services currently offered at Fire Station 1.
The two stations are designed to operate together as a coordinated emergency response system.
-
Fire Station 2 is typically staffed with three firefighters:
One Lieutenant
Two Firefighters
This staffing level allows the department to respond to calls using all of the apparatus at FS2.
-
Fire Station 2 contains three apparatus bays and currently houses:
Engine 2
Ladder 2
Squad Truck
Fire Alarm Truck
The station's apparatus bay space is fully utilized.
-
The Fire Department has long identified the ability to regularly staff an ambulance from Fire Station 2 as a future operational goal. Two firefighters/paramedics are needed to staff an ambulance. The Town has recently added firefighter/paramedic positions and continues to evaluate opportunities to strengthen EMS coverage throughout the community.
The station currently has sufficient dormitory space to accommodate additional personnel. However, there is not currently enough apparatus bay space to house an ambulance unless other apparatus are relocated.
-
Fire Station 2 was designed as a substation rather than a headquarters facility.
A substation provides emergency response coverage in a specific geographic area but does not contain all the administrative, training, support, and operational functions of a department headquarters.
For example, Fire Station 2 does not contain dedicated administrative offices, training facilities, maintenance facilities, or other functions currently located at Fire Station 1.
Fire Station 2
Project Costs and Funding
-
While the total project cost to construct a fire station at the former Deerfield has not been finalized, KBA has developed a rough order-of-magnitude cost for each of the three finalist sites. This comparative total project cost for Deerfield estimated $33,865,000 at the low end and $40,300,000 at the high end.
These figures will be preliminary until the project scope and budget are fully estimated, reviewed and approved. More detailed estimates will be developed over the coming weeks and months.
-
No.
While the design team has developed preliminary order-of-magnitude cost estimates, a final project budget cannot be established until schematic design is completed and site-specific engineering information is available.
The design team has been directed to develop the most efficient building possible while meeting the operational requirements of the Fire Department and the public safety needs of the community.
The current building program is approximately 20% smaller than the proposal considered in 2025. However, construction costs do not decrease due to reductions in square footage because many project costs—including site development, utilities, permitting, escalation, and contingencies—are not directly tied to building size. According to the Massachusetts School Building Authority, the cost of public building projects are impacted by annual inflation rates of 4 to 6%.
-
A new Fire Station 1 would likely be funded through municipal borrowing, subject to approval by Town Meeting and a debt exclusion vote. Additional funding opportunities are also being considered.
-
Yes.
The Town continually monitors state and federal funding opportunities and works closely with its legislative delegation.
Unlike school construction projects, Massachusetts currently does not have a statewide reimbursement program for fire station construction projects like the Massachusetts School Building Authority (MSBA).
Legislation has been proposed that would create a Municipal and Public Safety Building Authority. If such a program becomes available and Westwood qualifies, the Town would pursue any eligible funding opportunities.
Depending on the energy systems that are included in the project, there may be federal and state reimbursements available after the project is completed.
-
It depends on the timing of borrowing and the amount of non-borrowed funding (i.e. free cash) proposed in the Special Town Meeting article this fall. Realistically, taxpayers may not see an increase on their bills until FY28, but this timing will become finalized as Town Meeting approaches.
Project Schedule and Voting
-
The Select Board is considering a Town Meeting vote on October 26 and debt exclusion vote at the State Election on November 3.
-
Massachusetts law requires two separate votes for projects financed through a debt exclusion under Proposition 2½.
Vote 1 – Town Meeting
Town Meeting is Westwood's legislative body and is responsible for appropriating funds for municipal projects. This vote requires a 2/3 majority at Town Meeting.
At Town Meeting, voters will receive detailed information regarding the project scope, project budget, funding plan, and estimated residential tax impact before voting on the article.
A Town Meeting booklet containing information about the project will be mailed to all registered voters in advance of the meeting.
Vote 2 – Debt Exclusion Ballot
A second vote is required at the ballot box to authorize the Town to raise the funds necessary to repay the project debt outside the limits of Proposition 2½. This vote requires a majority.
Voters may participate through early voting, vote-by-mail, absentee voting, or in-person voting on Election Day.
An informational booklet explaining the ballot question will be mailed to all registered voters before the election.
-
The two-vote process ensures that:
Town Meeting reviews and approves the project and borrowing authorization.
All registered voters can approve or reject the associated tax impact.
Both approvals are required. If either vote fails, the project cannot proceed as proposed.
Massachusetts law does not currently allow these votes to be combined into a single vote.
-
In order to place a Proposition 2 ½ question (i.e. FS1 Debt Exclusion) on the state election ballot (“Midterm” on November 3rd), G.L. c.59, §21C(i) requires that notice be provided to the Secretary of the Commonwealth’s office first Wednesday in August preceding the state election, or, in this case, by August 5th. As such, the Board must vote to approve the form of the question and authorize it to appear on the state election ballot, that vote must be certified, and that certified vote and notice must be provided to the Secretary’ office no later than 5:00 p.m. on August 5th. Based upon this timing, the vote to place the question on the ballot must occur prior to the selection of the preferred site for the FS1 project.
The language for a Proposition 2 ½ debt exclusion question is highly regulated by law and would be the same regardless of the FS1 site recommended. The ballot language, shown below, is consistent with state law and the Town’s most recent ballot language for FS1:
Shall the Town of Westwood be allowed to exempt from the provisions of proposition two and one-half, so called, the amounts required to pay for the bonds issued in order to pay costs of designing, constructing, equipping and furnishing a new fire station, including the payment of all costs incidental and related thereto?
-
Yes.
As part of the Town Meeting process, the Finance & Warrant Commission will conduct public hearings and review the proposed project budget, funding sources, and estimated residential tax impact.
The project costs presented to voters this fall will include all remaining phases of the project, including:
Design development
Permitting
Bidding
Construction
Construction administration
Furniture, fixtures, and equipment
Contingencies and other project-related costs
The Town intends to provide voters with the most complete financial information possible before any vote is taken.
-
To maximize voter participation in this essential community decision. The decision to advance FS1 is one of the most consequential decisions facing Westwood, and the Select Board wants as many residents as possible to participate in voting on the FS1 debt exclusion. Reliable data shows that voter turnout in midterm elections is much higher than voter turnout in local elections which are deciding only state or local contests (the two FS1 ballots in 2025 drew 18-34% voter turnout; 2018 and 2022 midterms had 73 and 64% turnout, respectively). While history cannot guarantee future outcomes, this data suggests the question of FS1 will receive far broader participation as part of a midterm ballot than a municipal one.
For this reason, since there will already be midterm election in November, the Board decided to present the debt exclusion question to residents as part of that election.
Previous Design and Project Comparisons
-
Potentially, but additional design work is necessary.
The Town must evaluate operational requirements, site constraints, and community feedback before determining what revisions may be appropriate.
During the July 13th Fire Station 1 Steering Committee meeting, the committee supported a new program for the station that is a 19% overall reduction in the total net area. The former Deerfield Elementary School site was since named as the preferred location of Fire Station 1. With this location, the layout of a fire station on the property can vary greatly, as this site has the ability to accommodate drive-through apparatus bays, which decreases the number of bays necessary compared to an apparatus bay with only one means of access.
-
Each fire station is designed to meet the unique needs of the community it serves.
Factors affecting station size and layout include:
Staffing levels
Call volume
Apparatus requirements
Site conditions
Administrative functions
Modern building code requirements
Firefighter health and safety standards
Direct comparisons between communities often fail to account for these differences.
-
Previous estimates indicated that the project was generally consistent with comparable public safety facilities constructed in the region.
However, direct comparisons should be viewed cautiously because site conditions, project scope, inflation, and local requirements vary significantly from community to community.
Temporary Operations and Station Closure
-
The station was closed on February 26, 2026, after structural concerns were identified within the apparatus bay floor.
Following an emergency structural evaluation, engineers determined that bays two and three were no longer suitable to house large fire apparatus. All staffed apparatus and personnel were temporarily relocated to Fire Station 2, and operations resumed at Fire Station 1 in June following the installation of a temporary structure outside of the station.
-
The Westwood Fire Department’s presence, including overnight coverage, was restored to Fire Station 1 on June 1, 2026. After the closure, the Select Board approved plans to install a temporary structure outside of Fire Station 1, which allowed operations to resume at the station.
-
The closure has increased the urgency of finding a permanent solution, but it did not eliminate the need for careful planning, engineering, public engagement, and financial analysis.
-
No.
The temporary apparatus structure was installed to help maintain emergency response capabilities while the Town evaluates permanent solutions. It does not provide the full operational, administrative, training, health and safety, and support functions required of a modern fire station and is not intended to serve as a long-term replacement.
The temporary structure has also introduced additional challenges for the fire department. Water pools and could freeze in colder temperatures. The apparatus doors of the structure are close to the road, and firefighters stop traffic in front of the station to allow the apparatus to exit and return to the station. However, this can present safety concerns as some drivers block the box or drive around the apparatus as they attempt to pull out.
-
The Town has maintained the building over time, but it is a 78-year-old facility that has been in constant, heavy use 24 hours a day 365 days a year since it was built.
A fire station experiences very different wear than a typical house or building—the weight of fire apparatus, exposure to water, diesel exhaust, and the demands of a modern, 24/7 operation all take a significant toll.
Over time, those conditions have brought the building to the end of its useful life.
Recent structural issues, particularly with the apparatus bay floor, made that reality more immediate.
At this point, continued repairs do not solve the underlying problem—they only extend a facility that no longer meets today’s standards.
Even were it maintained to mint condition from the day it opened generations ago – it would be an antique, not an appropriate fire station for today’s needs, building codes, and accessibility standards.
Information, Communications, and Public Input
-
Project updates, reports, meeting materials, presentations, and announcements are available on the Town's Fire Station 1 project webpage.
Residents may also follow the Town through its social media channels and subscribe to the Westwood Wire newsletter.
-
Residents are encouraged to:
Attend public meetings
Participate in public forums
Submit questions and comments to FS1Committee@westwoodma.gov
Review project materials posted online
Community input remains an important part of the decision-making process.
-
Abutters have been and will continue to be notified through public meeting notices, project website updates, and direct outreach when appropriate. If you would like to meet with members of the FS1 Steering Committee, please email FS1committee@westwoodma.gov.
Additional public engagement will occur as site evaluations advance.
-
Following nearly a year of site evaluation, engineering analysis, public input, and FS1 Steering Committee review, the Deerfield School property was selected as the preferred location for a new Fire Station 1.
The site was selected because it best balances the Town's operational, financial, and long-term planning goals. Key factors included:
Ability to support emergency response objectives and maintain response times.
Sufficient site size to accommodate a modern fire station and future operational needs.
Ability to provide drive-through apparatus bays and improved vehicle circulation.
Opportunity to maintain uninterrupted fire operations at the existing station during construction.
Fewer site constraints than other locations evaluated.
Strong overall performance in the Committee's evaluation criteria.
Selection of a preferred site does not authorize construction. This decision allows the Town to focus design efforts on a single location, refine project costs, complete detailed engineering and environmental review, and prepare a final proposal for consideration by voters.
-
Town staff identified and evaluated a range of potential sites across the community based on criteria such as location, parcel size, accessibility, response coverage, and development potential.
The FS1 Steering Committee then evaluated eight of those sites in greater detail. These sites included the existing Fire Station 1 property, other municipally owned parcels, and privately-owned properties that could potentially accommodate a modern fire station.
-
The sites were selected based on factors including:
Geographic location relative to emergency calls
Ability to support emergency response times
Parcel size and configuration
Access to major roadways
Zoning considerations
Environmental constraints
Development feasibility
-
The three sites selected for additional evaluation were:
The Town-owned parcel 14-131 behind 736–738 High Street
The Deerfield School property at 72 Deerfield Avenue
The existing Fire Station 1 site at 637 High Street
-
The FS1 Steering Committee identified these sites as the most viable options based on:
Ability to support emergency response goals
Adequate site size and configuration
Potential for efficient apparatus access
Fewer development constraints than other locations evaluated
Ability to accommodate a modern fire station program
All are Town-owned parcels
-
Any site requiring new access to High Street would require additional engineering, traffic, legal, and permitting analysis. Potential solutions could include easements, frontage acquisition, or construction of new access roads.
These issues WERE evaluated as part of feasibility and schematic design.
-
The remaining sites were eliminated for one or more of the following reasons:
Insufficient site size
Operational impacts on other Town functions
Inability to support emergency response objectives
Significant development challenges
Environmental constraints
Excessive project costs
-
Yes. The Town conducted a broader review of potential locations and engaged with property owners where appropriate.
The eight sites selected for evaluation were those that best met the initial screening criteria. The Committee was open to new information but focused on the most viable options identified through the review process.
-
The location of a fire station directly affects emergency response times, which are critical to protecting life and property.
National Fire Protection Association (NFPA) standards emphasize the importance of rapid response. A well-located station helps ensure equitable emergency coverage throughout the community.
-
Yes.
The Committee has discussed co-location and shared facility concepts. However, fire stations have unique operational requirements, including apparatus circulation, emergency access, specialized support spaces, and 24-hour operations.
Broader discussions regarding multi-use facilities and long-term capital planning fall within the responsibilities of the Town's Long Range Financial Planning Committee and elected officials.
-
There is not sufficient space to do so. The existing police department lobby is very small and is more accurately a vestibule before getting into the one public meeting room and police operations.
Site Selection
-
The Town continues to work with environmental consultants and the Massachusetts Department of Environmental Protection (MassDEP) to understand the full scope of PFAS contamination identified at 637 High Street.
Additional testing is underway to determine the extent of contamination and evaluate potential remediation requirements.
Once the necessary data has been collected and analyzed, the Town will present the findings to MassDEP. MassDEP will ultimately determine what remediation measures, if any, are required.
-
No.
Regardless of whether Fire Station 1 remains at 637 High Street, the Town remains responsible for investigating and addressing environmental conditions at the property in accordance with MassDEP requirements.
The selection of Deerfield as the preferred site changes the future use of the property but does not eliminate the Town's environmental obligations.
PFAS and the Existing Fire Station Site
-
637 High Street
Lot Size: 1.02 acres
Benefits:
Direct access to High Street
No property purchase required
Minimal disruption to pedestrian and vehicle traffic
Minimal impact on town fields and recreation/open spaces
Access to existing utilities (water, electric, etc.) in place
Location is familiar to the Town and residents as a Fire Station
Challenges:
Requires temporary fire operations during construction
Lot size inadequate to accommodate drive-through bays
Less conducive to housing maintenance bay, front line apparatus, and training space
Less desirable lot topography
Site limits potential expansion in the future if needed
Lot 14-131
Lot Size: 5 acres
Benefits:
Highly accommodating to front line apparatus, training spaces, maintenance bay, and drive-through bays
Does not require off-site temporary fire operations
Minimal impact on town fields
Minimal lot restrictions
Challenges:
Access road from property to High Street needs to be evaluated
Could require Town Meeting approval for purchase of property to access High Street
Reduces access to nearby recreation areas and trails
Single road access to High Street